Huntsman sewer & venator project

Sewer Project
Ordering party:  Tebodin Netherlands B.V. in the name of Huntsman Holland B.V.
Contract price:    € 774.000,00 including changes
Schedule: April 2015 – December 2015 

Works: 
Concrete gutter, replacement of sewer pits by GRE, relining with GRE.  
The scope of work of the project Huntsman Sewer Renewal concerns mainly:
- Carrying out ground work in contaminated soil (class 1T1F);
- Replacement of sewer pits by GRE;
- Creating a concrete gutter in an existing concrete floor; 
- Applying of GRE sewer piping;
- Relining with GRE of existing piping and pits;
- Relining of an existing effluent pit with GRE sheeting;
- Recovering of pavements 

 

Venator Project
Ordering party:  Tebodin Netherlands B.V. in the name of Huntsman Holland B.V.
Contract price:  € 1.600.000,00
Schedule: August 2014 – March 2015 

Works: 
Ground work, concrete foundations and structural steel including fireproofing before, during and after the Turn Around. 
De scope of work of the project Huntsman Venator concerns mainly:  
- Ground work;
- Piling foundations;
- Concrete works and foundations;
- Structural Steel;
- Applying and recovering of Fireproofing 

The activities are carried out in three phases:
- Pre turn around.
- Just before turn around.
- During turn around. 


The works are realized in the MDI-1 and MDI-2 factory of Huntsman Holland B.V.


Tags
  • Petro Chemical