De Nieuwe Deltagoot

Client Deltares Vastgoed & Bouwzaken   
Contract sum € 14,396,342.00   
Building time September 2012 – November 2014      

 

Scope of which generally consist of:
The concrete gutter constructed for the new research facility has the following measurements; length of 300 meters, width of 5 meters and depth of 9.5 meters. The construction is located for 90% under ground level. Parallel to the gutter is a covered reservoir. Realized with the same measurements as the gutter. There are 2  pump chambers within this reservoir. Furthermore, another function of this concrete cover over the parallel gutter is the reachability alongside the gutter.  

Engineering and realization for underground casing construction through:
- Temporary sheet piling with screen frame;
- Return pumping incl. license section;
- Vibro combination piling; 
- Complete concrete constructions, incl. 2 wall and floor dilatations.  

Special concrete construction query: accuracy of 3 millimeter at 300 meter. Furthermore, extensively collapsing facilities on behalf of measure activities; 

Additional executed activities:
- Detailed design and execution of pumps, piping and appendages;
- Construction hall 48x29x12m with a special section door(12x5x10m)  implemented; 
- Control building (40x9x6m)
- Incline breakwater 

Coordination of activities conducted by third parties:
- Wave board installation;
- Portal Crane incl. rails;
- Compartmentalization bulkheads;
- Electra, instrumentation, measure and control technics
- Site completion

Location

Delft

Project Information

Project Owner: Deltares Vastgoed & Bouwzaken

Project Phase: Opgeleverd

Construction Time: 2012 - 0001

Function category: Infra droog – besloten terrein,Infra droog